what you need to do when you received cold roll forming machine

Sep 09, 2025

Here is a comprehensive, step-by-step guide on what you need to do, from the moment the truck arrives to the first production run.

Phase 1: Pre-Arrival Preparation (Before the Truck Arrives)

This is the most critical phase. Failure here causes major delays.

  1. Review Documentation: Study the foundation drawings, electrical requirements, and overall layout provided by the manufacturer. Know the machine's weight and dimensions.

  2. Prepare the Foundation: The floor must be perfectly level and strong enough to support the machine's weight (often several tons). Anchor bolts should be pre-set according to the drawing's exact specifications.

  3. Ensure Utilities are Ready:

    • Electrical: Have a certified electrician install the correct power supply (voltage, phase, amperage) with a main disconnect switch at the machine location.

    • Compressed Air: Ensure an adequate air supply line (with correct pressure and CFM) is run to the location, including a filter/regulator unit for clean, dry air.

  4. Arrange Equipment: Have the right equipment ready for unloading:

    • A forklift or overhead crane with sufficient capacity for the heaviest crate.

    • Slings, shackles, and spreader bars rated for the load.

    • Pallet jacks, crowbars, and tools for uncrating.

  5. Designate Personnel: Assign a team (including maintenance and future operators) to be responsible for receiving and installation.


Phase 2: Upon Receipt & Unloading

  1. Visual Inspection of Crates: Before signing anything, inspect all crates and packaging for signs of damage during transit (e.g., broken wood, crushed corners, torn packaging). Note any visible damage on the Bill of Lading before you sign it. Take photos as evidence.

  2. Unload with Extreme Care: Use your planned equipment to carefully unload each crate. Move them to a clean, dry, and level area near the installation site. Avoid sudden impacts or drops.

  3. Inventory Check:

    • Unpack the crates methodically.

    • Check all parts, components, and accessories against the Packing List provided by the manufacturer.

    • Look for any cosmetic or functional damage to the machine itself (e.g., bent shafts, scratched rolls, damaged electrical panels).

    • Immediately report any discrepancies or damage to the manufacturer and the shipping company.


Phase 3: Installation & Commissioning

This phase is typically done with the support of the manufacturer's installation engineers.

  1. Positioning: Move the main machine and auxiliary equipment (decoiler, cutting table) into their precise positions on the prepared foundation.

  2. Leveling & Anchoring: Using precision levels, level the machine perfectly in all directions. This is non-negotiable for machine performance and longevity. Once level, tighten the anchor bolts to secure it.

  3. Connecting Utilities: Have your electrician connect the power to the machine's main panel. Connect the compressed air line.

  4. Mechanical Assembly: Assemble the various components:

    • Install the decoiler and feed guide.

    • Install the forming mill stands onto the main shaft.

    • Assemble the hydraulic unit and cutting saw.

    • Connect all drive shafts and guards.

  5. Lubrication: Fill all gearboxes, bearings, and lubrication systems with the correct type and grade of oil/grease as specified in the manual.

  6. Commissioning by Engineer: The manufacturer's engineer will:

    • Perform a thorough check of all electrical connections.

    • Test the rotation of all motors to ensure they are correct.

    • Check the alignment of all forming stations and the cutting saw.

    • Test the hydraulic and pneumatic systems.

    • Run the first test production. This is where they will fine-tune the machine, set up the basic parameters, and produce the first samples.


Phase 4: Training & Acceptance

  1. Operator Training: Ensure your operators and maintenance technicians are present for the commissioning. They must be trained on:

    • Basic operation and control panel functions.

    • How to change forming rolls and set up for a new profile.

    • How to adjust the cutting length and troubleshoot common issues (e.g., material twisting, poor cutting).

    • Daily maintenance procedures (e.g., lubrication, cleaning).

  2. Acceptance Test: Run the machine with your chosen material to produce samples. Verify that the finished product meets your required dimensions (section geometry, length tolerance, etc.). Only sign the acceptance certificate once you are fully satisfied.

Phase 5: Going Forward

  1. Create a Maintenance Schedule: Based on the manual, create a schedule for daily, weekly, and monthly maintenance (checking bolts, lubricating, inspecting wear parts).

  2. Stock Spare Parts: Identify and order critical spare parts (e.g., shear blades, specific bearings, seals) to minimize future downtime.

  3. Keep Records: Document all production runs, setup changes, and maintenance activities.

By following these steps meticulously, you ensure a smooth transition from receiving a large crate to producing high-quality profiles efficiently and reliably.